The below list is an outline of road improvement projects in Okeechobee County:
11/06/24: Public Notice - ROADWAY RESTRIPING ON COUNTY ROADS RECENTLY PAVED
Project: Roadway striping on county roads recently resurfaced.
Start Date: Friday - November 8, 2024
End Date: Tuesday - November 19, 2024
Locations:
1. SE 86th Blvd(15A)-Okeechobee Hammock Area
2. NE 7th St, NE 8th St, NE 10th St, NE 13th St, NE 15th St and NE 17th St-Douglas Brown Area
3. SE 38th Ave and SE 6th St- Conners Gable Area
4. NW 7th St- Okeechobee Park Area
5. NW 9th St- Lawrence Industrial Area
6. SW 144th Pkwy- River Oak Acres
7. SW 13th St- Lazy 7 Area
8. SW 28th Terrace- Pine Acres Area
9. NW 72nd Ave- Dinner Island Rd
10. NW 364th Rd, NW 8th Terrace and NW 366th Trail-Ft. Drum Area
This project is being completed by our contracted striping vendor, Southwide Industries.
As this is a moving operation, impacts to traffic will be minimal.
Drivers are urged to proceed with caution and obey all traffic and warning signs in the project areas.
For more information contact the Okeechobee County Public Works Department/Road & Bridge Division.
Phone: 863-763-3514
Approved by: Darren Brown, Public Works Director
Email: mgarcia@okeechobeecountyfl.gov
Website: www.okeechobeecountyfl.gov
==============================================================================
9/25/24: 2024 ANNUAL COUNTYWIDE ROADWAY RESURFACING (PAVING) PROJECT
Okeechobee County and our contracted paving vendor, C.W. Roberts Contracted, Inc., have scheduled the County’s annual road paving project to begin on Tuesday, September 24th, 2024 and is expected to be completed by the end of October 2024. The list of all roadways, intersections and road cuts that were approved by the Board of County Commissioners to be paved are shown below.
Please note that the approved paving schedule may change depending on weather and other factors over this expected project time period.
Drivers are urged to take caution and plan ahead to allow for more time to pass through these areas as the traffic volume on surrounding streets may be higher than usual.
Message Boards will be used to alert drivers to the project area and to proceed with caution.
For additional information regarding this project, please visit the County’s website at www.okeechobeecountyfl.gov or contact the Public Works Department – Road & Bridge Division at E-mail: mgarcia@okeechobeecountyfl.gov and/or Office Phone: (863) 763-3514.
Project Contact:
Darren Brown, Public Works Director
E-mail: dbrown@okeechobeecountyfl.gov
Michelle Garcia, Administrative Assistant Public Works Department
Office: (863) 763-3514
E-mail: mgarcia@okeechobeecountyfl.gov
ANNUAL ROADWAY RESURFACING (PAVING) PROJECT LOCATIONS:
NE 8th St from NE 16th Ave to NE 14th Ave
NE 7th St from NE 15th Ave to NE 14th Ave
NE 15th Ave from NE 8th St to NE 12th St
NE 10th St from NE 16th Ave to NE 14th Ave
NE 13th St from NE 16th Ave to NE 17th Ave
NE 17th Ave from NE 13th St to NE 15th St
NE 15th St from NE 17th Ave to NE 16th Ave
SE 38th Ave from SE 6th St to SE 37th Terr
SE 6th St from SE 36th Terr to SE 40th Ave
SE 86th Blvd(15A) from US 441 to Hwy 710
NW 96th Ct from NW 80th Ave to the end
NW 7th St from NW 18th Av to end
NW 9th St from SR 98 to city limits
SW 144th Pkwy & SW 16th Dr.
SW 13th St from SW 67th DR to the end
SW28th Terrace from SW 8th St to end
NW 72nd Ave from new asphalt to the end
NW 364th RD from SR 441 to NW 4th Dr
NW 8th Terr from NW 364th Rd to NW 366th trail
NW 366th trail to the end at the turnpike
NE 301st Blvd from NE 304th St to NE 48th Ave
NE 48th Ave from NE 301st Blvd to NE 304th St
NW 240th St(Eagle Island) 700A intersection
SE 66th Ave end of road(cul-de-sac)
**Note: Roadway striping work will begin following the completion of the County’s Annual Resurfacing (Paving) Project. This project is expected to begin in December 2024.
Approved by: Darren Brown, Public Works Director
Prepared by: Michelle Garcia, Administrative Assistant
==================================================================================
Posted 4/12/24: Lofton Roadway Improvement Project
Engineering-Survey Work Underway - Completion: Early 2025
Construction Commencement: Early Summer 2025
Construction Completion: Early Summer 2027
Lofton Road Improvement Project - Phase 1 - Road Design
The County has begun the design and engineering phase for the Lofton Road Improvement Project, which is a $7.1 Million project that is funded through a Florida Department of Transportation (FDOT) Small County Outreach Program (SCOP) grant. This project will include needed roadway safety and drainage improvements to Lofton Road, from the US Highway 98 west to the Railroad Tracks, approx. ½ mile from the Kissimmee River.
Those who utilize this roadway will begin to see crews in the project area (i.e., survey, etc.) to assist with the design and engineering for this important safety project. No lane closures are expected but crews may be working near the travel lane. Please use caution in the area and watch for workers in the work zone.
The design and engineering phase of this project is expected to be completed by Spring 2025 (subject to weather conditions and other variables).
The bidding of this project and the start of construction is expected to begin by Fall/Winter 2025 (subject to weather conditions, bidding approval, and other variables).
The County will continue to provide updates on the Lofton Road Improvement Project within the Okeechobee County Board of County Commissioners website – www.okeechobeecountyfl.gov – as well as on our various social media sites. Once construction is approved, signage will be installed within the area to notify the community of road work beginning.
The proposed design/engineering phase of this 5.189 mile project includes: contract administration, management services, construction engineering inspection services, quality acceptance reviews of all work associated with the development, preparation of the contract plans and construction of the resurfacing and associated improvements.
Some of the major improvements that are proposed within this project include:
. Milling and Resurfacing or Overlaying the existing travel lanes according to County specifications
. Pavement and shoulder widening, as appropriate
. Construct roadway improvements, as identified in approved plans
. Furnish and install drainage improvements
. Provide signing and pavement markings
Note: All services performed would be in accordance with all applicable Florida Department of Transportation (FDOT) manuals, guidelines and specifications.
For additional information and/or questions regarding this project, please contact Mr. Darren Brown, Public Works Director, at dbrown@okeechobeecountyfl.gov or Tel: 863.763.3514 Ext. 6104 and/or Mr. Stef Matthes, County Engineer, at smatthes@ct-eng.com.
=================================================================================
Posted: 11/30/23: Driveway pipe replacement and drainage work: Pine Ridge Park area - Single lane closure (one-lane access) PROJECT COMPLETED.
Start Date: Tuesday, December 5, 2023
End Date: Thursday, December 21, 2023
Location: Pine Ridge Park Area-This project will involve driveway pipe replacement and drainage work with partial lane closures on NE 28th Ave (Ellerbee Rd), NE 29th Ter, NE 30th Ave, NE 31st Ter and NE 11th Lane. The single-lane closures are necessary to allow equipment to replace driveway pipes and conduct drainage work.
This project is being completed by the Okeechobee County Public Works Department - Road & Bridge Division, which is expected to provide cost savings to our taxpayers.
Drivers are urged to follow the directions of the flag men, drive with caution and plan ahead to allow for more time to pass through the area as the traffic volume on surrounding streets may be higher than usual.
Message boards are going to be placed in the project area to alert drivers of the work zones and provide updates on work progress.
For more information visit the Okeechobee County website or contact the Okeechobee County Public Works Department/Road & Bridge Division at:
Phone: 863-763-3514
Email: mgarcia@okeechobeecountyfl.gov
Website: co.okeechobee.fl.us
====================================================================================
2023 ANNUAL COUNTYWIDE ROADWAY RESURFACING (PAVING) PROJECT
PROJECT COMPLETED
ANNUAL COUNTYWIDE ROADWAY RESURFACING (PAVING) PROJECT
Okeechobee County and our contracted paving vendor, C.W. Roberts Contracted, Inc., have scheduled the County’s annual road paving project to begin on Monday, August 14, 2023 and is expected to be completed by September 2023. The list of all roadways, intersections and road cuts that were approved by the Board of County Commissioners to be paved are attached.
Please note that the approved paving schedule may change depending on weather over this expected project time period.
Drivers are urged to take caution and plan ahead to allow for more time to pass through the area as the traffic volume on surrounding streets may be higher than usual.
For additional information regarding this project, please visit the County’s website at www.co.okeechobee.fl.us and/or contact the Public Works Department – Road & Bridge Division at E-mail: mgarcia@co.okeechobee.fl.us and/or Office Phone: (863) 763-3514.
Project Contact:
Justin Hoover, Assistant Public Works Director
Michelle Garcia, Administrative Assistant Public Works Department
Office: (863) 763-3514
E-mail: mgarcia@co.okeechobee.fl.us
Approved by: Rich Reade, Deputy County Administrator
Prepared by: Michelle Garcia, Administrative Assistant
ANNUAL ROADWAY RESURFACING (PAVING) PROJECT SCHEDULE
8/15-8/17 |
MICCO BLUFF ROAD |
NW 285TH WAY FROM NW 160TH DRIVE (MI LL/REPAI R) |
|
|
NW 285TH WAY FROM NEW JOI NT TO CURVE (MI LL/REPAI R) |
|
|
NW 285TH WAY FROM END OF PAVEMENT BACK 700 FT (MILL/REPAI R) |
|
|
|
8/19 |
GOLF COURSE |
NE 131ST LANE FROM SR 441 TO END (PRIVATE GOLF COURSE) |
|
|
|
8/21-8/22 |
TAYLOR CREEK ISLES |
SE 29TH STREET FROM SE 18TH TERRACE TO CUL-DE-SAC |
|
|
SE 30TH TERRACE FROM JOI NT@ 441 200 FT TO NEW JOINT |
|
|
|
8/23-8/29 |
FOUR SEASONS |
NE 70TH AVE FROM JOINT@ SR 70 TO JOINT@ NE 5TH STREET |
|
|
NE 7TH STREET FROM NE 70TH AVE TO CUL-DE-SAC |
|
|
NE 5TH STREET 180 FEET WEST FROM NE 70TH AVE |
|
|
NE 80TH AVE FROM SR 70 TO NE 13TH WAY |
|
|
NE 13TH WAY TO 82ND AVE |
|
|
NE 82ND AVE FROM NE 13TH WAY TO NE 12TH LANE |
|
|
NE 12TH STREET FROM NE 82ND AVE TO NE 80TH AVE |
|
|
NE 80TH AVE FROM NE 12TH STREET TO EAST CENTER STREET |
|
|
SE 80TH AVE FROM EAST CENTER STREET TO SE 8TH STREET (END) |
|
|
|
8/30- 8/31 |
WHISPERING PINES |
NW 39TH CIRCLE FROM NW 36TH STREET TO NW 36TH STREET |
|
|
|
9/1 & 9/4 |
PLAYLAND PARK |
NE 46TH AVE FROM NW 30TH STREET TO NW 18TH STREET |
|
|
NW 11TH DR FROM JOINT@ NW 46TH TERR TO END OF PAVEMENT AT NW 42ND AVE |
|
|
|
9/5-9/6 |
BASSWOOD |
NW 33RD AVE FROM NW 36TH STREET TO NW 24TH LANE |
|
|
NW 30TH AVE NORTH SIDE OF 36TH STREET TO CUL-DE-SAC |
9/7 |
LAZY SEVEN AREA |
SW 87TH TERRACE FROM SR 70 TO SW 9TH STREET |
|
|
|
9/8 |
CONNERS HIGHLANDS |
NW 22ND LANE FROM NW 5TH AVE TO NW 7TH AVE |
|
|
NW 21ST LANE FROM NW 5TH AVE TO NW 7TH AVE |
|
|
|
9/11-9/12 |
RUCKS ROAD (NW 34TH AVE) |
NW 164TH COURT FROM NW 34TH AVE TO END |
|
|
NW 168TH COURT FROM NW 34TH AVE TO END |
|
|
NW 172ND COURT FROM NW 34TH AVE TO END |
|
|
NW 33RD TERRACE FROM NW 32ND AVE TO END |
|
|
|
9/14-9/15 |
DIXIE RANCH ACRES |
NW 81ST COURT FROM NW 80TH AVE TO CUL-DE-SAC |
|
|
NW 80TH COURT FROM NW 80TH AVE TO CUL-DE-SAC |
|
|
NW 83RD COURT FROM NW 80TH AVE TO CUL-DE-SAC |
|
|
|
9/18-9/20 |
OKEECHOBEE GARDENS |
NE 48TH AVE (ENTIRE ROAD) |
|
|
|
9/25-9/26 |
C. SCOTT DRIVER PARKING LOT |
OLDER SECTION OF PARKING LOT |
|
|
|
TBD |
EVERGREEN CEMETERY |
ROAD IN NORTHERN SECTION OF CEMETERY |
**Note: Roadway striping work will begin following the completion of the County’s Annual Resurfacing (Paving) Project. This project is expected to begin in September/October 2023
================================================================================
Road construction, drainage work: Partial Road closure (one-lane access) at NW 344th Trail
PROJECT COMPLETED
Location: NW 344th Trail
Time frame: Monday, April 25, 2022, at 7:30 AM to Thursday, April 28, 2022, at 5:00 PM (weather permitting).
Okeechobee County has scheduled a partial road closure (one-lane access will be provided) at
NW 344th Trail, to replace the existing drainage pipe to improve storm water drainage within the
area. Traffic is planned to be provided with one-lane access on NW 344th Trail for the duration
of the project.
This project is being completed by our County Public Works Department - Road & Bridge
Division, which is expected to provide a cost savings to our taxpayers.
Drivers are urged to follow the directions of the flag men, drive with caution and plan ahead to
allow for more time to pass through the area as the traffic volume on surrounding streets may
be higher than usual.
For more information contact the Public Works Department/Road & Bridge Division
Phone: 863-763-3514.
================================================================================
Road construction, drainage work at NE 342nd Trail:
PROJECT COMPLETED
Location: NE 342nd Trail
Time frame: Monday, April 18, 2022 at 7:30AM to Thursday, April 21, 2022, at 5:00PM (weather permitting).
Okeechobee County has scheduled a road closure at NE 342nd Trail between NE 4th Drive and NE 7th Drive, to replace the existing drainage pipe to improve stormwater drainage within the area. Traffic is planned to be detoured to NW 366th Trail (a/k/a Osowa Road) for the duration of the road closure.
This project is being completed by our County Public Works Department - Road & Bridge
Division, which is expected to provide a cost savings to our taxpayers.
Drivers are urged to follow the directions of the flag men, drive with caution and plan ahead to
allow for more time to pass through the area as the traffic volume on surrounding streets may
be higher than usual.
For more information contact the Public Works Department/Road & Bridge Division
Phone: 863-763-3514.